It's going to be messy around here for awhile. The streets are being worked on. The work is to be performed by H & R
Paving, Inc., within the following areas:
Location A: US 1 and Grand Avenue and between SW 27 Avenue and McDonald
Street
Location B: Grand Avenue and Oak Avenue and between Gifford Lane and Mary
Street
Location C: Matilda
Street from Bird Avenue to just South of Jackson Avenue
The project consists of
asphalt/pavement restoration and reconstruction, storm sewer
improvements, to include the installation of French drainage systems and
cleaning and desilting existing drainage structures, and pavement markings and
signage within the construction limits. Based on the nature of the
construction work, there will be times when the residents will be informed of
parking restrictions needed to allow the construction activity to be performed.
Crews will complete the project in sections to minimize
traffic congestion and allow for pedestrian access as much as
possible.
Contractor began mobilizing Monday and will take approximately
160 days to complete the project. Please note that
this schedule could change due to bad weather or other unexpected
conditions. No surprise there.
The work will be done from 8 am to 5 pm Monday thru Friday. There may be lane closures or delays.
YOU MAY NOT LIFT THE PHOTOS & TEXT. IT'S COPYRIGHTED INTELLECTUAL PROPERTY. YOU CAN HOWEVER SHARE A STORY ON SOCIAL MEDIA BY USING THE LINKS HERE.
For linking to this one story, just click on the time it was posted & just this story will open for sharing - only through social media. Not copying and pasting.
0 Comments:
Post a Comment
<< Home